Long Islanders fume over utility's storm response

Text Size: AaAaAaAaAa

(Continued from Page 1)

LIPA, whose board is chosen by the governor and lawmakers, contracts with National Grid for service and maintenance. Last year, its board chose a new contractor, New Jersey's Public Service Enterprise Group, which will take over in 2014. Gov. Andrew Cuomo criticized the storm response of all New York utilities in the region, saying their management had failed consumers.

Asked Monday about LIPA board vacancies he hasn't filled and whether he takes responsibility for what's happening there, Cuomo called the authority a holding company that became "an intergovernmental political organization." He said National Grid was the actual Long Island power provider, one of the monopolistic state-regulated utilities. "They're going to be held accountable," he said, citing lack of communication and preparation and even proposing they consider rebates instead of rate hikes.

A state report criticized LIPA in June for poor customer communications after Irene last year and for insufficient tree trimming. The Department of Public Service noted major problems in telling customers estimated power-restoration times, faulting its computer system, which a consultant had found deficient back in 2006.

LIPA acknowledged that customers aren't getting the information they need, partly because of the system, which it is updating. Authority officials said the new system will be operating next year.

"It is a huge computer system. After Irene we immediately accelerated that process, and even at that it is still an 18-month to two-year process," LIPA's chief operating officer, Michael Hervey, said Monday. "We would have liked to have had it up and running for now, but it's just such a large magnitude computer system that it takes that long."

Hervey said the company will be working with remaining customers over the next several weeks as they get their homes repaired. "They can't be safely re-energized from an electrical standpoint," he said. "We are ready to service those areas, but they are not ready to take it right now."

John Bruckner, president of National Grid Long Island transmission and distribution, said he had about 15,000 people working on restoration, including 6,400 linemen from all over the U.S. and Canada.

Matthew Cordaro, co-chairman of the Suffolk Legislature's LIPA Oversight Committee and a former utility executive, said Con Ed and Public Service Electric & Gas New Jersey did a good job responding to the storm, and LIPA didn't.

Copyright 2013 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Reader Poll

What's your favorite campfire food?

s'mores
hot dogs
marshmallows
other