Boeing official: 787 flight resumption up to FAA

Published: Friday, March 15, 2013 12:30 p.m. CST • Updated: Friday, March 15, 2013 12:56 p.m. CST

Boeing expects to finish testing its battery fix for the 787 within the next week or two. Then it will be up to the Federal Aviation Administration to decide when the planes fly again.

That assessment from Ron Hinderberger, Boeing’s vice president for engineering on the 787, was more cautious than statements from other company officials, who suggested Thursday that the 787 could be flying within weeks.

Boeing is testing several changes to the plane’s lithium-ion battery aimed at preventing overheating and a fire — conditions that led to the global fleet of 787s being grounded for the past two months.

Hinderberger said Friday that there will be one flight test. Most tests will be done on the ground, and all should all be done in one to two weeks.

Get breaking and town-specific news sent to your phone. Sign up for text alerts from the Northwest Herald.

Reader Poll

How far are you traveling this Christmas holiday?
more than 200 miles
between 200 and 100 miles
less than 100 miles
staying home