Mostly Cloudy
67°FMostly CloudyFull Forecast

Crews work to repair Lake Decatur dam

Published: Thursday, Sept. 26, 2013 7:49 a.m. CDT • Updated: Thursday, Sept. 26, 2013 9:03 a.m. CDT

DECATUR — The latest round of work on the Lake Decatur dam is underway and will include a barrier aimed at keeping invasive Asian carp at bay.

The $4 million project is set to be finished by fall 2014.

The (Decatur) Herald & Review reports the first phase of the project was completed in 2011.

The latest round of work includes fixing concrete and repairing erosion damage. Meanwhile, crews will also remove a failed tailwater dam, which was built more than a century ago.

Keith Alexander is director of water management in Decatur.

He says replacing the entire Lake Decatur dam would cost more than $60 million, so it's more cost-efficient for crews to do "preventative maintenance" work every five to 15 years.

Get breaking and town-specific news sent to your phone. Sign up for text alerts from the Northwest Herald.

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Reader Poll

How do you support breast cancer awareness?
Donate money
Register for a run
Wear a pink ribbon or other apparel
Other
I don't